A contractor that's left millions of dollars in park construction projects incomplete in Fayetteville appeared to have insured itself, while legal action is pending, according to city records.
The $13.4 million Mazarick Park tennis center project ... construction of a community center at Mable C. Smith Park The building framework materials are set to be delivered this week, allowing ...
Additional funds to finish the Mazarick Park tennis center project were approved ... who assured her that construction on the building would continue even if additional funds for the project ...
Seventy-First High School Principal Myron Williams suffered third-degree burns at Mazarick Park in Fayetteville. Officials said Williams was trying to light the grill when he opened the lid and ...
City records show that tennis court light work at Mazarick Park was complete as of January 2024 and that redesign for the tennis center was in progress. In July 2023, the building completion date ...