News

In October, the school district informed parents it was considering the strategy at five secondary schools because of significant enrolment growth. It says that Burnaby North Secondary will not ...
Imagine you’re about to get your high school yearbook picture taken and you really ... Generally speaking, high school seniors in the North became much more likely to dress differently from ...
In February 2024, the new $117 million Burnaby North Secondary School — a seismic redevelopment and expansion — opened. The high school redevelopment has 1,800 seats, making it one of the largest ...
The structural steel company that worked on the new Burnaby North Secondary School is suing the school district and Yellowridge, the school's prime builder, for $2.8 million in alleged unpaid work ...
A subcontractor that worked on the new Burnaby North Secondary School, which opened to students this week, is suing the Burnaby school district and the school's main builder. Surrey-based PMC ...
Surrey's PMC Builders & Developers Ltd. claims it is owed nearly $2.8 million in unpaid work, materials and 'extras' under a subcontract for the construction of the new Burnaby North Secondary School.
The new Burnaby North Secondary School will have universal washrooms, for example, but there will also be some more traditional, gendered washrooms, according to the district. Universal washrooms ...
The new Burnaby North Secondary School will have universal washrooms, for example, but there will also be some more traditional, gendered washrooms, according to the district. Universal washrooms were ...
The Burnaby school board is suing its lead consultant and structural engineer for extra costs and construction delays in the $108-million Burnaby North Secondary School replacement project.
Construction is underway at the future site of the new Burnaby North Secondary School. Cornelia Naylor The Burnaby school board is suing its lead consultant and structural engineer for extra costs and ...